Progress as of Nov. 7
Lots of things have been done since this summer. Here is a recap of where I’m at on various projects:
- Building PVC frames for windows and doorway: 10% (I’ve measured them and bought pvc…)
- Building two 24-channel light controllers: 95% (Just need to clean them up and mount them.)
- Building 48 channel controller for RGB+W Flood lights: 0%
- Building 4 RGB+W flood lights: 90% (Need to mount red LEDs and test them. Look for a post about them coming soon!)
- Make 48 extension cords for light controllers: 100%
- Sequence music: 15% (Almost done with first song! Then, four left… this takes FOREVER!)
- Solder FM Transmitter, create antenna, and test: 0%
- Make or have made sign for FM signal: 0%
- Create two eight-channel giant arches: 0%
Those are the things I can think of off the top of my head. Hopefully everything will come together, but I’m seriously doubting that I will be ready to go live the day after Thanksgiving at this point. I’m shooting for the first week of December now. We will see!
Comments are closed.